Friday, March 22, 2019
March 2019 - Part 2
Thursday, March 21, 2019
March 2019 - Part 1
Saturday, February 23, 2019
Febraury 2019
A few weeks ago the traffic from 42 North going to 295 N was re-routed into the newly constructed tunnel. Here you can see the three lanes going into the tunnel where they merge down into two. The traffic lights are normally green and are only used when they need to close a lane in the tunnel
The tunnel walls are lined with a large number of lights. The number of lights that are turned on seems to vary by the time of day.
At the other end of the tunnel, paving work is being done to get ready for when the 76 East ramp lanes are re-routed into the tunnel.
Work continues on the retaining wall about the tunnel
Work also continues along 42 North by the ramp from 295. This is where the ramp from 42 North to 295 North will eventually go.
Sunday, February 3, 2019
February 2019
The most activity recently has been around the new tunnel along 295 North. By the time you read this traffic coming off of 42 North will have been re-routed into this tunnel. Over the next few weeks the ramp from 76 East will be re-routed into that tunnel also which will free up room to continue construction of the main line overpass.
Some finishing work has been done at the end of the tunnel. The hill side has been cleaned up and covered in stone and a railing as been added to the top of the retaining wall.
Friday, January 4, 2019
January 2019
Here is a look at the entrance to the tunnel that will eventually carry the 76 West to 295 North ramp. Short term all the traffic lanes going north on 295 will route through here to make room for other construction. On the right you can see the retaining being capped off.
Since that picture was taken traffic lights have been added before the tunnel. I believe these will be used to open and close lanes in the tunnel.
Now that the tunnel is complete they are using the top to provide access needed to finish the top of the retaining wall.
Construction continues on the retaining wall between 42 and the cemetery. At the end of the wall are the supports for the 295 main line overpass.
A new section of noise barrier has been built along the cemetery.
Work continues just below the Browning Road overpass. Part of a noise barrier has been constructed and work continues on foundations for more supports for the main line overpass.
Sunday, December 16, 2018
December 2018
Here is a look at the 76 East to 295 North tunnel. You can see a concrete pumper pouring the last section of the roof. The used plastic to wall off the section of the tunnel where the roof was being poured. I assume this was done to control the temperature.
A new section of retaining wall has been started just south of the Browning Road overpass.
They have also started a new section of noise barrier in this area.
Here is the view of the wall from the back.
Here are some views of the work along 42 South taken from the Browning Road overpass.
The area along the church parking has been cleaned up. I assume this will eventually get re-paved.
Here is a look at the supports for the 295 main line near the cemetery. They have recently started to construct retaining wall around the supports.
Here is a wider view of that area. On the far right are foundations for new noise barrier.
The supports for the temporary Browning Road overpass have been complete of quite some time now but there hasn’t been any more progress on the overpass since then.
Wednesday, November 21, 2018
November 2018
Work continues on the tunnel that will carry the traffic coming from 76 East under the new 295 main line
The beams for the roof of the tunnel were set a couple weeks ago then covered in corrugated steel and recently that have started pour the concrete roof. In the upper right you can also see some new noise barrier work.
Paving has been done in the area after the tunnel.
The support columns for the new 295 mainline.
Work in the area between the Al-Jo curve and the Browning Road overpass is almost complete for now. The area has been paved and a fence installed on top of the retaining wall.
There is still a lot of work going on below the Browning Road overpass
The have started to excavate some pits in this area which I assume are going to be for support columns for the main line overpass.