Sunday, April 23, 2017

April 2017

A temporary fence has been installed at the corner of the church on Browning Road. this area will be used to connect to the temporary bridge over 76.

DSC02037

DSC02038

 

The land on the other side of 76 has been cleared to provide access to the other side of the temporary bridge

DSC02041

 

Work is also being done at the corner of Browning Road and Willow Place.

DSC02039

 

The shoulder along 76 East just below Browning Road has been widened and paved.

20170422_162831_001

Sunday, April 9, 2017

April 2017

Things have been pretty quiet on the project for the past few months, but they are going to start picking up now that the 3rd contract has started.

 

Let’s start with the progress on 2nd contract.

Here is the work going on between the north and south bound lanes of 295 between Bell Road and the Al-Jo curve. Drainage work is being done along with preparations for a new sign structure.

DSC02006

 

Here is the new sign structure waiting to be installed. It will go over the south bound lanes.

DSC02019

 

This picture was taken from the new ramp from 295 S to 76 W. On the left you can see the path that the new ramp from 76 E to 295 N will take. You can also see the new ramp over 76 in the distance.

DSC02021

 

DSC02023

 

The structure of the new 76 E to 295 N ramp was completed a few weeks ago and decking work is currently under way.

DSC02028

 

Land clearing along Essex avenue has begun for one of the two new sections of the Bellmawr Park Mutual Housing. This will be used to relocate the units that will need to be removed the project.

DSC02030

 

A new temporary wood fence has been constructed at the corner of the cemetery just before the 76 overpass. This area will be used to access the new temporary bridge over 76 that will be needed while the existing bridge is reconstructed. 

DSC02032

Excavators in that same area.

DSC02033

Monday, February 6, 2017

February 2017

The new ramp from 295 South to 76 West opened over the weekend. Going south on 295 all three lanes of traffic now go up the new ramp that has been built right before the Al-Jo curve.

DSC01973

 

Shortly after the start of the ramp the road goes from 3 to 4 lanes.

DSC01975

 

The lane split with the left two lanes going to 76 West and the right two lanes continuing onto the Al-Jo curve and then to 42 South/295 South.

DSC01976

 

Here is the ramp to 76 West. Eventually this ramp will split and also become the new 42 South ramp.

DSC01978

 

Progress has also been made on the new 76 East to 295 North ramp. The steel now extends over 76 West. Only last last section over 76 East needs to be completed.

DSC01984

Tuesday, January 31, 2017

January 2017

The new ramp along 295 South just above the Al-Jo curve has been widened and the Jersey barriers have been moved over to get ready for the opening of the new lanes.

DSC01951

 

This is where the new ramp will split to become the new ramp to 76 West. Most of the paving is done and the noise barrier installation is under way. Eventually all traffic will go down this ramp which will split to go to both 42 South and 76 West, but the 42 South portion will not happen for a few more years.

DSC01970

 

Here is a look at the new ramp from the existing 76 West ramp.

DSC01961

 

Installation of the steel for the new 76 East to 295 North ramp is proceeding. The first pieces that are partially over 76 have been installed.

DSC01967-b

 

 

 

DSC01967

Saturday, January 28, 2017

Bellmawr Park Mutual Housing

As part of the next phase of the direct connect project 12 units of Bellmawr Park Mutual Housing will need to be relocated to make way for the new ramp from 76 east to 295 south.  The map below shows where the units will be relocated to, 6 units will go into each location.  This article has more information including the plans for each area.

http://southjerseyobserver.com/12-bellmawr-park-mutual-housing-units-to-be-replaced-relocated/

 

You can find the Zoning Board resolution concerning this project.

http://www.egovlink.com/public_documents300/bellmawr/published_documents/Zoning%20Board%20Minutes/2016/2016%2006%20bellmawrPark%20Resolution.pdf

 

image

Tuesday, January 24, 2017

Browning Road Re-construction

Bids recently closed on the third contract for the direct connect project and work should begin on this contract in the next few months. One of the major parts of this phase will be the re-construction of the Browning Road overpass over 42 to widen the space under the bridge. This will be done by first building a temporary bridge just north of the existing one. The old bridge will be torn down and reconstructed and finally the temporary bridge will be removed. To accommodate this work there will also be a small re-alignment of Willow Place.

 

image

Sunday, January 1, 2017

December 2016 Pictures

The new ramp along 295 South just before the Al-Jo curve is being widened. This will eventually serve as the ramp to both 76 West and 42 south.

DSC01917

 

DSC01927

 

Here is a look at the new portion of the ramp that has been recently construction. This will soon replace the existing ramp to 76 West.

DSC01923

 

Here is a look at the ramp from the current ramp to 76 West.

 

DSC01937

 

DSC01938

 

The first pieces of steel are being put in place for the new 76 East to 295 North ramp.

DSC01943

 

DSC01944