Saturday, August 9, 2014

St Mary’s Cemetery Area

A lot of the work on contract two is happening in an unused section of St Mary’s Cemetary in Bellmawr. There has been a lot of land clearing and excavation going on in this area.

 

IMG_4848

Here is a view of the area from the Browning Road overpass.

IMG_4845 

The construction access road off of Browning Road.

 

IMG_4741

Another shot of the area from the Browning Road overpass.

IMG_4728

Looking at the St Mary’s area from 295 North.

IMG_4843

Drilling rig at the back of the cemetery. 295 North is just beyond those trees.

Sunday, August 3, 2014

295 North Ramp

 

Part of contract 1 is to build a new ramp from 295 N to 76 West to replace the existing ramp. This ramp is currently being built right next to the existing one.

IMG_4840

Land has been cleared next to the start of the old ramp and they have begun the work to construct the support for that side of the ramp.

IMG_4839

This picture shows the new support that has been constructed between the North and South bound lanes of 42.

IMG_4817

This column between the interim ramp and the old ramp will hold a support for this end of the new ramp.

IMG_4841

Here work is being done on the support for the other end of the ramp which is between the old ramp and the new interim ramp.

Saturday, August 2, 2014

295 Black Horse Pike to Al-Jo Curve

Here is an update on the work along 295 from the Black Horse Pike to the Al-Jo curve.

 

Work continues along 295 Southbound right before the curve. This will eventually become the beginning of a new ramp that will take 295 S to with 76 West or 42 South this replacing the Al-Jo curve.

IMG_4768

IMG_4746

IMG_4771

 

Contract 2 has recently started which will include major work on this section of 295. You can start to see some of the preliminary work for this. Here is the 295 North exit to the Black Horse Pike. They have cleared all the trees inside the ramp loop. There has also been some work done in the area in the foreground which up till now has been used as a staging area.

IMG_4823

 

They have started to remove the noise barriers along 295 Northbound.

IMG_4824

Thursday, July 31, 2014

Bell Road Overpass 7/2014

With two construction contracts currently underway there has been a lot of activity recently, so I will cover the current progress over the course of a couple posts. Let’s start with the work on the Bell Road overpass. The second half of the bridge is now well underway.

 

IMG_4743

Here you can see the new center support under construction. Since this picture was taken the columns have been complete and they have started working on the cross piece. In the background you can see the old support on the 295 Northbound side. They have started to build the new one behind the old one and have just started taking out the old one.

 

IMG_4797

The support on the 295 Southbound side appears to be complete.

 

IMG_4744

Here’s another picture of the support on the 295 Southbound side. You can also see the rebar on the side of the finished section of the road.

Friday, July 4, 2014

Google Street View

Google Street View has recently been updated in the construction zone. The update is from sometime in the Fall of 2013. The aerial view is till showing the area pre-construction.

 

Here is an image from Street View showing the work on the Bell Road bridge.

 

image

Thursday, June 5, 2014

Photo Update May 2014

IMG_4571

42 North just before the 295 north bound ramp to 42. They are in the process of building the supports for the new ramp that will go along the side of the old one. You can just see the rebar cages for the support columns behind the red container.

IMG_4597

Another view of the same area. The yellow cylinders are forms for the support columns.

IMG_4600

Piles being driven in between the new interim ramp to 295 North and the old 295 North to 42 ramp. I assume this will also be part of the new ramp.

IMG_4601

A closer view of this work.

IMG_4585

The new retaining wall along 42 North between the 295 ramps. Not much going on here at the moment.

IMG_4592

They continue to raise the area next to 295 South right before the Al-Jo curve. It appears that the new highway will be a bit higher then the current one.

IMG_4605

They have started to construct the paths to the temporary pedestrian bridge over 42 next to the Creek Road overpass. Work to re-construct this overpass will likely start soon.

IMG_4665

The median between 295 North and South, South of Essex Ave has been paved right up to the new Essex overpass and a new median barrier has been installed. This barrier was cast in place so it probably permanent. They have also prepped the land on the other side of the Essex Ave overpass and it looks like it will be paved soon.

IMG_4576

This container recently showed up along 295 by the Black Horse Pike. Conti is the contractor for the second phase of the construction and they have already started work. They appear to be doing some work around the Blackhorse Pike exit, and have also started to do some land clearing in other area.

IMG_4658

Land has been cleared by the 76 North to 295 North along the Al-Jo curve.

IMG_4663

They have started to clear the trees along St Mary’s Cemetery.

Saturday, April 12, 2014

Photo Update 4/12/2014

Here are some pictures from the last two weeks.

 

IMG_4524

First half of the Bell Road overpass is complete and now being used by traffic. Work doesn’t appear to have started yet on the other side.

 

IMG_4550

 

IMG_4552

IMG_4551

A lot of work going on along side 295S just before the Al-Jo curve. The new retaining wall is being installed and they have started to back-fill the area to bring it back up to the finished road height. The south bound lanes of 295 will eventually shift out into this are as work continues.

 

IMG_4558

 

IMG_4556

These pictures were taken from the Al-Jo curve looking back towards 76. A new retaining wall has been constructed along 76 separating it from the pond within the curve.

 

IMG_4534

A concrete paving machine was installed at the Essex Ave overpass last week. Since then is has been removed, so I believe the concrete has been poured for the overpass deck.

 

IMG_4518

Paving work has been going on in the median between 295 North and South just south of Essex Ave.

 

 

IMG_4522

The temporary pedestrian bridge has been installed over 42 next to Creek Road. This will carry pedestrians and utilities while the re-construction of the Creek Road over pass is done. This will work just like Bell Road where half the bridge is demolished and re-build while the other half carries one-way traffic.

 

IMG_4538

Another show of the pedestrian bridge from 42. In the background you can also see work going on along the ramp from the southern portion of 295 to 42 North. Eventually a new ramp will be built next to the old one.

IMG_4543

Another shot of the work going on at the 295 ramp to 42 North.

 

IMG_4542

Work going on along the new interim ramp fro 42 North to 295 North.

IMG_4546

They have started installing new noise barriers along the interim ramp.